Location
Cumilla
Year
2024
Delivery time
16 weeks

Outcome

Passed custody-transfer calibration first time

Four custody-transfer metering skids sourced from the Netherlands with witnessed FAT.

The challenge

A fixed mobilization date left no room for delays at the port. The client needed certified equipment, correct documentation and a single point of accountability.

Our solution

We split the order across two approved manufacturers, arranged witnessed inspection, pre-lodged customs documents and staged delivery to site in the order the crew needed it.